| Project Research and Development Timeline | ||
|
Once you become an ElectroRally team, you will need to develop a timeline for completion of your project. To help you in planning, following is a sample timeline that we have developed based on experiences of teams who have participated in past ElectroRally competitions. This timeline is a good starting point, but we suggest that you develop a more detailed timeline. |
||
|
Two Semesters Program |
||
|
October 1 |
|
Organize team members and sign Student Team Contract |
|
November 1 |
Make list of team activities and complete vehicle design | |
|
December 1 |
Secure sponsorship (if desired) and procure all vehicle parts |
|
|
February 1 |
Car should be 50% complete |
|
|
March 1 |
Team report should be submitted and car should be 90% complete | |
|
March 15 |
Begin testing car | |
|
April 15 |
Car testing and refinements should be complete | |
|
One Semester Program |
||
|
January 5 |
Organize team members and sign Student Team Contract | |
|
January 30 |
Make list of team activities and complete vehicle design |
|
|
February 15 |
Secure sponsorship (if desired) and procure all vehicle parts | |
|
March 1 |
Team report should be submitted and car should be 50% complete | |
|
April 1 |
Car should be 90% complete | |
|
April 15 |
Begin testing car | |
|
May 1 |
Car testing and refinements should be complete | |